Sprint planning: how to plan a sprint step by step
Last updated
Sprint planning is the meeting that starts a sprint. The team decides what it will work on for the next one or two weeks and agrees a goal for it. Good sprint planning takes an hour or two and saves many interruptions later.
What is sprint planning for?
It answers two questions:
- What can we finish this sprint? The team picks items from the top of the product backlog.
- How will we do it? The team breaks each item into tasks small enough to finish in a day or two.
Who takes part
- The product owner explains what matters most and why.
- The developers decide how much they can take on. This is their decision.
- The Scrum master keeps the meeting to its time.
How much work to take on
Look at how much the team finished in the last few sprints. That number is its velocity. Plan to about that amount, and a little less if someone is away. A sprint that is too full ends with unfinished work every time.
Plan a sprint in Menejar AI
Menejar AI works as the sprint planning tool and the board, so the plan you make is the board you work from.
- Open the project’s backlog. It lists tasks with the most important first.
- Create a sprint. A new, empty sprint appears above the backlog.
- Move tasks into the sprint. Drag tasks from the backlog into the sprint.
- Start the sprint. Give it a name, a goal and its start and end dates, then start it.
- Work from the board. The Scrum board now shows the sprint.
At the end of the sprint
Complete the sprint from the backlog or the board. Tasks that are not done can move to the next sprint or return to the backlog. The burndown chart and the velocity report then show how the sprint went, which is the number you plan the next one with.